Project Description


The proposed works involved the replacement of an existing timber glazed wall to an external cycle shelter located on a footbridge, with a new GRP panelling system.

VEDA were employed by Spence to check the Form 002 / 003 for the main temporary works design by others.

This also involved checking the capacity of the existing steel bridge beams for the increased loading imposed by the temporary works, as well as the proposed loadings onto the existing platform.

Project Details


Project Name: Horley Station Scaffold Design Under Bridge
Type of Project: Scaffold Design
Client: Spence
Date completed: November 2014 


Services provided:     

  • Rail Engineering
  • Temporary Works
 
 
 

Related Projects


 
 
kingsford river bridgescaffold design under bridge

kingsford river bridge
scaffold design under bridge

 
seven sisters stationRaking Shores to Retaining Wall

seven sisters station
Raking Shores to Retaining Wall

 
dunton green stationPolystyrene Plant Bridge

dunton green station
Polystyrene Plant Bridge