Project Description


The embankment slip near Stonegate station in February 2014 was a deep seated rotational slip and caused 40m of the Down line between Wadhurst and Stonegate to be removed.

The remaining Up line remained intact but with a 3.0m high shear face in the embankment fill emanating from the sleeper ends.

As part of the embankment stabilisation scheme to which VEDA Associates were employed by Dyer and Butler Ltd as lead designer the Up line was to be temporarily supported such that engineering vehicles could deliver materials further slip locations on the line.

A gabion wall was designed and constructed supported on the piling mat. This allow the line to reopen to engineering vehicles within 10 days. 

 

Project Details


Project Name: Stonegate Station 
Type of Project: Gabions
Client: Dyer & Butler
Date Completed: March 2014 


Services provided:     

  • Structural Engineering & Architecture
  • Civil Engineering
  • Rail Engineering
  • Temporary Works
 
 

Related Projects


 
 
stonegatePipe jacking 

stonegate
Pipe jacking 

 
slymlakes level crossingtrack stability 

slymlakes level crossing
track stability 

 
locipPlatform extensions 

locip
Platform extensions